In the course of a day the building started out looking like this:
Friday, February 26, 2010
Tuesday, February 23, 2010
Mid-Week Twelve
The above photo, taken Tues. Feb. 23rd is of the south side (back) of the building, which faces an alley.
Friday, February 19, 2010
Sneak Peek from the Inside
Photo was taken in early evening.
East side main entrance
Capital Plumbers and TGC Electricians have been working inside the building this week. The roofers are close to getting all the shingles on the roof. Framing is almost complete. Behind the scenes, USDA RD has approved 2nd pay out for construction and architects totalling $94,766.35.
Capital Plumbers and TGC Electricians have been working inside the building this week. The roofers are close to getting all the shingles on the roof. Framing is almost complete. Behind the scenes, USDA RD has approved 2nd pay out for construction and architects totalling $94,766.35.
Monday, February 15, 2010
Beginning Week 11
Monday was another busy day at the library construction site. Framing crew is working inside, more roofing material was delivered, and the crew on the roof is laying tar paper in preparation for shingles. We met with Tom the electrician to finalize outlet, port and switch plans. All interior and exterior materials have been selected. We're growing accustomed to the mud. The photo above shows the addition of the covered walkway at the main entrance on the east side of the building.
(Photo by Terry Davis, J.W. Elmer Construction)
Friday, February 12, 2010
USDA Rural Development Grant
We just received some great news! John Lynn, area Representative from Coeur d'Alene USDA Rural Development was present at the Feb. 11th City Council meeting to announce the approval of additional grant funds of $38,000!! We are grateful for USDA's support of this building project especially in light of the area's difficult economic situation. There are costs associated with the building that were not included in the basic construction bid such as disposal of the old building, landscaping, shelving, parking lot, architectural & engineering fees and administration. USDA is also financing the library bond at a lower rate of interest than we would have been able to obtain through traditional financing methods.
Wednesday, February 10, 2010
Getting Ready for a Roof
During the past few days the framing crew has been nailing down plywood sheeting in preparation for the roof. Again we have been blessed with great weather for outdoor construction. Library staff took a "tour" of the inside of the building Tuesday morning to gain a perspective of where rooms will be located. Wednesday afternoon USDA Rural Development Staff visited to inspect progress. USDA Rural Development is handling our bond financing and they are providing additional ARRA funds to assist with completion of the project. Your comments are welcome.
Above left photo was taken Friday Feb. 6th prior to placement
of plywood sheeting on roof. Photo on right is from Wed. Feb. 10th
as framers are getting close to finishing up their portion of the roof.
More photos from Wed. Feb. 10th. Photo on left is a view
from the northwest. Photo on right was taken from southeast
side of building.
Thursday, February 4, 2010
Bird's Eye View
We're thankful for the great weather as the construction crew continues to work on trusses. (No wind, rain or snow, and mild temperatures) The above photos were taken Thursday afternoon. Though Elmer Construction set an aggressive completion date for their crews, we are approaching the end of the 9th week of the project on schedule for the city's targeted date of May 31st.
Wednesday, February 3, 2010
Time for Trusses
Trusses were delivered Tuesday morning. The photos show progress made in just a few hours. These guys are hard workers!
Monday, February 1, 2010
Framing Continues
Thanks to Terry from James Elmer Construction for sending the pictures he took today. (I forgot my camera) Workers enjoyed 40 degree weather and the mud soup is beginning to dry out. Roof trusses should be delivered this week. Water and sewer lines have been connected to the building. We are accepting estimates for shelves.
From the inside looking out to the north
North side of the building viewed from D Street
From the inside looking out to the north
North side of the building viewed from D Street
Subscribe to:
Posts (Atom)