Welcome

We are excited to share our project with you. This construction project has been a goal of the Library Board for over ten years. The new library will better serve Plummer's citizens and patrons from the surrounding area. Please come back often to check out the progress through photos.

Tuesday, December 22, 2009

Week Three Update








The foundation was complete by the end of the third week. The snow only lasted a day so work was done in the rain.




Thursday, December 17, 2009

And Then it Snowed


December 15th was a little snowy although it did not last long.

More Foundation Pouring Shots







Tuesday, December 15, 2009

Progress Week Two


The second full week on the project was a busy one. Crews finished digging the basement area.

The basement is only under a small portion of the Library to provide much needed storage.






Forms and rebar were put into place.

















And they were ready to pour.








Tuesday, December 8, 2009

December 7th


Accelerated Construction and Excavating is moving right along on the earth work.

Ready...Set...Begin...




We were all very excited to see the equipment moved in and ready to begin work.